Doral City Hall 5.jpg

Location:
Flagler Real Estate Development, LLC
City of Doral, FL

Schedule:
Project Start Date: 2011
Project Completion Date: 2012

Cost:
Project Cost: $22 million
Square Footage: 62,371 SF

Involved Companies

Precast Concrete Producer

Metromont Corporation
P.O. Box 2486
Greenville, SC 29602
https://www.metromont.com/
Email Metromont

Architect

Hunton Brady Architects
400 North Ashley Drive
Tampa, FL 33602
https://huntonbrady.com/

General Contractor

Flagler Construction
6144 NW 74th Avenue
Miami, FL 33166
https://construction.altaequipment.com/page/flagler

Engineer

DDA Engineers
4930 SW 74th Court
Miami, FL 33155
https://www.ddaeng.com/

Background

The new Doral City Hall complex was developed to provide a sustainable, updated facility for the city’s governmental services.  The new three-story facility was built on a 1.8 acre project site right across the street from the old city hall which was half the size of the new building.  The Doral City Hall was designed and achieved LEED Silver certification and featured a 250 parking space garage, epicenter for events, training facility, and facilities for businesses to lease. Metromont Corporation provided 497 precast components to help complete the Doral City Hall project.

Benefits of Precast:

  • Speed of construction

  • Cost effective

  • High quality architectural finishes

  • Durability

  • Reduced site disturbance

  • Less trades/coordination.

Total Pieces of Precast: 497